In case you are aware there is a B.E.S.S. located in Poland that is not included in our list, please use CONTACT >> button to let us know.
| Location | Date of Commissioning | Rated Power | Capacity | Manuufacturer / Supplier | Owner |
|---|---|---|---|---|---|
| Puck | 2016 | 0,75 MW | 1,50 MWh | Qumak S.A. | Energa Operator |
| Bystra | 2019 | 6,00 MW | 27,00 MWh | Hitachi | Energa Wytwarzanie |
| Lubachów | 2019 | 0,50 MW | 2,00 MWh | My-Soft | Tauron EkoEnergia |
| Cieszanowice | 2019 | 3,00 MW | 0,70 MWh | Leclanche / Griffin Energy | Tauron Dystrybucja |
| Bełchatów | 2020 | 1,00 MW | 1,00 MWh | brak danych | PGE GIEK |
| Rzepedź | 2020 | 2,10 MW | 4,20 MWh | Tesla / Griffin Energy | PGE |
| Garbce | 2021 | 5,50 MW | 1,20 MWh | MySoft Impact Clean Power Technology | PKP Energetyka |
| Góra Żar | 2021 | 0,75 MW | 0,50 MWh | brak danych | PGE Energia Odnawialna |
| Kamień Śląski | 2022 | unknown | 1,00 MWh (?) | M.E.B. | unknown |
| Zielona Góra | 2022 (?) | unknown | Enea | ||
| Opalenica | 2022 (?) | unknown | Enea | ||
| Bydgoszcz | 2022 (?) | unknown | Enea | ||
| Bydgoszcz | under construction | NRG Project | Enea | ||
| brak danych | under construction | Neo Energy Group | PGNIG | ||
| Żarnowiec | public tender in process | 205,00 MW | 820,00 MWh | PGE | |
| Lotnisko | planned | 23,00 MW | 46,00 MW | PGE | |
| Bukowo | planned | 26,00 MW | 52,00 MW | PGE | |
| Karnice | planned | 11,00 MW | 22,00 MWh | PGE | |
| Zwałowisko | planned | 8,50 MW | 17,00 MWh | PGE | |
| Jeziorsko | planned | 2,00 MW | 4,00 MWh | PGE | |
| Warta | planned | 2,00 MW | 4,00 MWh | PGE | |
| Kamieńsk | planned | 10,00 MW | 20,00 MWh | PGE | |
| Brzóza Stadnicka | w planach | 1,50 MW | 3,00 MWh | PGE | |
| Cisna | w planach | 2,00 MW | 4,00 MWh | PGE | |
| unknown | grid conditions issued | 133,00 MW | 532,00 MWh | Columbus | |
| unknown | grid conditions issued | 62,70 MW | 250,80 MWh | Columbus | |
| unknown | grid conditions issued | 202,44 MW | 810,18 MWh | Columbus | |
| Rymanów | grid conditions issued | 110,00 MW | 440,00 MW | Green Capital | |
| unknown | grid conditions issued, capacity market auction | 21,00 MW | unknown | OX2 | |
| Ząbkowice Śląskie | grid conditions issued | 80,00 MW | unknown | confidential | |
| Ełk | grid conditions issued | 5,00 MW | 20,00 MWh | KSME | |
| Turośń Kościelna | grid conditions issued | 200,00 MW | 800,00 MWh | KSME | |
| Siedlce | grid conditions issued | 200,00 MW | 800,00 MWh | KSME | |
| Lubaczów (?) | grid conditions issued | 5,00 MW | 20,00 MWh | KSME | |
| Konin | grid conditions issued | 200,00 MW | 800,00 MWh | KSME | |
| brak danych | grid conditions issued | 5,00 MW | 20,00 MWh | KSME | |
| Dolna Odra (?) | grid conditions issued | 500,00 MW | 2000,00 MWh | KSME | |
| several locations | grid conditions issued | total approx. 500,00 MW | unknown | OX2 | |
| several locations on Tauron DSO | grid conditions issued | total approx. 120 MW | unknown | confidential | |
| Kozienice | grid conditions issued | około 100 MW | unknown | confidential | |
| Kielce | grid conditions issued | około 100 MW | unknown | confidential | |
| Karolinów | grid conditions issued | 220 MW | unknown | confidential | |
| Sieroniowice | grid conditions issued | 8 MW | unknown | confidential | |
| Jaroszowice | grid conditions issued | 8 MW | unknown | confidential | |
| Jędrzychów | grid conditions issued | 1 MW | unknown | confidential | |
| Zawiercie | public tender awarded | 5 MW | 13 MWh | Elemental Holding | |
| Czernikowo | public tender awarded | 1 MW | 2 MWh | EST Energy / Energon Advanced Energetics | confidential |
| several locations in Poland | grid conditions issued | 262 MW | unknown | confidential | |
| three locations | unknown | approx. 500 MW | unknown | PGE |